On a project, money is made through claims, not rates. We prepare FIDIC claims and support contractors on PEC, procurement, guarantees and disputes.

Contract and engineering documentation (illustrative image)Illustrative
Contract and engineering documentation. Illustrative image, not an AHS project.

Services

What we handle

FIDIC claims

FIDIC 1987, 1999 and 2017: EOT, delay, variation, escalation, payment and IPC claims, with 28-day notices.

Arbitration consultancy

DAAB and arbitration support for contract disputes.

Contract administration

Notices, records and claim timelines kept on track through the project.

PEC advisory

PEC registration and renewal, engineer registration, category upgrade.

Tender, PQ & EPADS

PPRA / EPADS compliance, e-bidding, prequalification, technical and financial bids.

Bank guarantee & credit line

Support for bank guarantees, credit line and financial limits, and JV setup.

FIDIC Red Book 2017

Your rights as a contractor

  • Clause 2.4 Employer must show within 28 days, on request, that funds exist for the whole works; otherwise the contractor may slow down or suspend (16.1) and claim the delay and cost.
  • Clause 1.9 / 2.1 Late drawings or late site access: time and money.
  • Clause 4.12 Unforeseeable sub-surface conditions: cost borne by the Employer.
  • Clause 8.5 / 8.6 Delay not caused by you: EOT is your right and LDs do not apply.
  • Clause 8.9 Employer suspends work: recover idle machinery and staff cost.
  • Clause 13.3 Work outside the BOQ is a separate variation with separate payment.
  • Clause 13.6 / 13.7 Changes in tax or law, or steel and cement price rises: escalation.
  • Clause 14.7 / 14.8 IPCs due within 56 days; late payment carries financing charges.
  • Clause 16.2 Employer default: right to terminate.
  • Clause 18 Protection in exceptional events such as floods or war.
  • Clause 20.2 Notice within 28 days, fully detailed claim within 84 days, or the claim is lost.
  • Clause 21 DAAB and arbitration.

Read the full FIDIC claims guide

AHS Constructions is PEC registered and works in FIDIC 2017 and its 2022 reprint; claim fees are on success (as stated on the existing FIDIC page).

Payment stuck? Claim time running?

Under Clause 20.2 the notice is due within 28 days. Talk to us before it lapses.